Changing Status Using the Reviewer Interface

Reviewers using the Astoria Reviewer interface to display a document that is in a workflow can change its workflow status.

For information about workflow, see About Astoria Workflow.
  1. While viewing a document in the Reviewer interface, click .
    When viewing an individual DITA topic in the Reviewer interface, clicking allows you to change the workflow status of the topic. However, if the topic is referenced by a map that has a status set, you cannot set the status of the topic lower than the map's status level.

    When viewing a DITA map in the Reviewer interface, clicking only applies to the map's status. If your repository is configured to change the workflow status on documents referenced by a map, changing the status of the map also changes the status of its referenced topics. See Setting Workflow Status on Documents Referenced by a Map.

    If the document is in a workflow, the Change Status dialog appears.


    The work-flow-related fields in the dialog will vary, depending on how the workflow is configured. Make selections in these fields, as appropriate for the workflow configuration.

  2. Select a New Status.
    The available states are defined in one or more Task Sequence documents inherited by the object.
    Note: Some status changes may not be available for a topic if the Task Sequence document for a transition is defined to allow changes only from a map that references the topic. See Setting Workflow Status on Documents Referenced by a Map.
  3. Make selections in the Assign to or Audience fields, as appropriate for the workflow configuration.
    These fields are enabled only if the Task Sequence document Status changer chooses audience option is selected.
    • The Assign To field is enabled if the transition specifies a Task Owner.
    • The Audience field is enabled if the transition specifies a Task Audience.
    • Both fields are enabled for a parallel workflow.
  4. Accept the default Due Date for the next job step, or change it to a new date and time.
  5. If desired, enter a Job Note that will be included in the job ticket comment field.
  6. Enter a Snapshot Label or select one from the list.
    Settings in the Task Sequence document control whether this field is enabled and if so, how this field is used.
  7. If you are applying a Snapshot to a document that references other documents, select the Apply label to referenced documents check box.
    If the check box is cleared, the snapshot label will be applied only to the object.
  8. If you are applying a Snapshot to a document that references other documents, select the If this label exists on referenced objects, update it to use the new timestamp check box.
    If the check box is cleared, all referenced objects that already have this snapshot label will not have the timestamp modified with that of the selected object. However, the selected object will have the timestamp changed to the date specified here.
  9. Click OK.
  10. If your organization requires electronic signatures for snapshot labels or for changing a status, you are prompted for your credentials. You must enter the same credentials that were used to log into Astoria, then click OK.